C7K - Approve Commission Chamber Renovations
View full title
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING SUPPLEMENTAL NOS. 2 AND 3 TO THE CONSTRUCTION CONTRACT BETWEEN THE CITY AND LEE CONSTRUCTION GROUP, INC., PURSUANT TO CONTRACT NO. 19-257-06 FOR THE COMMISSION CHAMBER RENOVATION PROJECT, INCREASING THE TOTAL CONTRACT AMOUNT TO $2,405,481.91; AND FURTHER, WAIVING, BY A 5/7TH VOTE, THE FORMAL COMPETITIVE BIDDING REQUIREMENT, FINDING SUCH WAIVER TO BE IN THE CITY'S BEST INTEREST, FOR THE PURCHASE, IN THE AMOUNT OF $262,862.65, FOR THE REMAINDER OF THE NON-CONTRACT ITEMS NECESSARY TO COMPLETE THE PROJECT.
Sponsors
Commission Vote Result
7-0
PASSED